Allahabad High Court Orders Return or Compensation for Excess Land Possession in NCRTC Acquisition Dispute

LAW FINDER NEWS NETWORK | |
Allahabad High Court Orders Return or Compensation for Excess Land Possession in NCRTC Acquisition Dispute

Court directs fresh demarcation to resolve discrepancies in land acquisition for RRTS Corridor; excess land taken by NCRTC in Plot No. 277 to be returned or compensated, while possession of unacquired land in Plot No. 276 permitted as per award


In a landmark judgment delivered on 12th November 2026, the Allahabad High Court (Division Bench comprising Justices Siddhartha Varma and Kunal Ravi Singh) adjudicated a dispute concerning land acquisition carried out by the National Capital Region Transport Corporation (NCRTC) under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The case involved the acquisition of portions of two plots – Plot No. 276 and Plot No. 277 – situated in Village Sivaya, Jamaullapur, Tehsil Sardhana, District Meerut for the construction of the Delhi-Ghaziabad-Meerut Regional Rapid Transit System (RRTS) Corridor.


The petitioner, Bal Kishan, claimed ownership and possession of the plots and challenged the NCRTC’s possession of land beyond the acquired area, particularly in Plot No. 277. The contention arose from discrepancies in demarcation reports, with NCRTC allegedly taking possession of 644 sq. meters in Plot No. 277 against an acquired area of only 320 sq. meters, while taking possession of lesser land in Plot No. 276 than acquired.


The Court, after carefully examining multiple demarcation reports and noting inconsistencies in earlier surveys, directed a fresh demarcation to be conducted under its supervision. The final report dated 12th January 2026 revealed that NCRTC had indeed encroached upon an additional 324 sq. meters in Plot No. 277 while possessing 324 sq. meters less in Plot No. 276 than what was officially acquired.


Upholding the petitioner’s rights, the Court ordered NCRTC to return the excess land in Plot No. 277 to the petitioner forthwith or, alternatively, pay adequate compensation determined by the concerned authority after providing notice and hearing. Simultaneously, NCRTC was permitted to take possession of the remaining 324 sq. meters in Plot No. 276 as per the acquisition award. The Court declined to pass any order relating to the demolition of the petitioner’s boundary wall, leaving the petitioner free to pursue remedies available under law.


This decision emphasizes the necessity of strict adherence to the demarcation process in land acquisition and the protection of landowners’ rights even in projects of national importance. The judgment also underscores that any possession beyond the acquired area must be either restored or compensated in accordance with law.


Bottom Line:

Land acquisition under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Dispute over demarcation of acquired and unacquired land - Fresh demarcation report directed by Court to resolve discrepancies - Excess land possession must be returned or compensated adequately.


Statutory provision(s):

Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013; U.P. Revenue Code, 2006 (Section 80); Constitution of India (Article 226)


Bal Kishan v. Union of India, (Allahabad)(DB) : Law Finder Doc Id # 3033337