Telangana High Court directs prompt construction of Integrated District Court Complex at Jogulamba Gadwal

Court emphasizes access to justice as a fundamental right under Article 21, orders improved interim facilities for advocates and litigants amid construction delays


In a significant judgment delivered on November 13, 2026, the Telangana High Court (Division Bench comprising Mr. P. Sam Koshy, A.C.J. and Mr. Suddala Chalapathi Rao, J.) addressed a Public Interest Litigation (PIL) concerning the prolonged delay in the construction of an Integrated District Court Complex at Jogulamba Gadwal. The petitioner, Advocate K. Shafiulla, represented by Ms. Pujari Srilekha, sought directions to the State authorities to expedite the construction and improve existing court infrastructure.


The Court acknowledged that the land measuring 10 acres at Sy.No.368, Pudur Village, Jogulamba Gadwal, was duly sanctioned and possession handed over to the Judicial Department with all administrative sanctions in place, including a substantial budget allocation exceeding Rs. 81 crores, later revised to Rs. 99.28 crores. Despite the appointment of a contractor and completion of necessary formalities, the construction work had yet to commence, causing inconvenience to the judicial officers, advocates, litigants, and court staff.


Highlighting the constitutional mandate under Articles 14 and 21 of the Indian Constitution, the Court reiterated that access to justice is an indispensable element of the right to life and liberty. The lack of adequate infrastructure in the existing court premises, especially the absence of separate washrooms for women advocates, litigants, and staff, was held to be a violation of dignified access to justice.


While the Court refrained from imposing rigid timelines for the project's commencement and completion, it urged the concerned departments to avoid further delay and initiate construction at the earliest. In the interim, the Court directed the State authorities to ensure the provision of essential amenities, including segregated washrooms for women, within the current court premises to uphold the dignity of all court users.


The judgment underscores the importance of infrastructure development in the judicial sector as a prerequisite for effective judicial functioning and access to justice. It reflects the judiciary's proactive stance in safeguarding constitutional rights by holding administrative authorities accountable for infrastructural inadequacies.


Bottom Line:

Access to justice is an essential facet of the right to life under Article 21 of the Constitution of India. Establishment of Integrated District Court Complex is necessary for effective judicial functioning and ensuring proper access to justice. Authorities must ensure timely construction and provision of adequate temporary infrastructural facilities in existing Court premises.


Statutory provision(s): Constitution of India, Articles 14 and 21


K. Shafiulla v. State of Telangana, (Telangana)(DB) : Law Finder Doc Id # 3129690