Court affirms that objections on road alignment were duly considered, emphasizing limited judicial review unless mala fides or legal violations are proven under the National Highways Act, 1956
In a significant judgment dated November 13, 2026, the Telangana High Court (Division Bench) dismissed a writ appeal filed by Talasani Sravan Reddy challenging land acquisition proceedings for the Kalwakurthy Bypass Road on National Highway No.167K. The Court held that objections raised by the petitioner regarding the road alignment were duly considered and rejected by the competent authority, and reiterated the limited scope of judicial review in land acquisition cases under the National Highways Act, 1956.
Background:
The appellant, Talasani Sravan Reddy, is the recorded owner of one acre of converted agricultural land in Survey No.509 of Kotrasivar Village, Nagarkurnool District, Telangana. The land was notified for acquisition as part of the Kalwakurthy-Kollapur Section widening project for NH No.167K, sanctioned by the Government of India for an estimated cost of Rs. 886.69 crores.
The appellant contended that as per the final Detailed Project Report (DPR) map, the Kalwakurthy Bypass commenced from chainage (CH) 76/400, which would exclude his land from acquisition. However, the acquisition notification and project alignment proceeded from CH 76/100, thereby including his land unnecessarily. He alleged that the competent authority failed to properly consider his objections and mechanically rejected them without adequate reasoning.
Legal Proceedings:
Initially, the appellant’s father had challenged possession attempts through a writ petition in 2022, which was disposed of with a direction to follow due process for acquisition. Subsequently, acquisition proceedings under Sections 3A, 3C, and 3D of the National Highways Act, 1956, were initiated. The Revenue Divisional Officer (RDO), acting as Competent Authority for Land Acquisition (CALA), notified the acquisition, heard objections on October 17, 2022, and issued endorsements addressing the appellant’s objections.
Despite this, the appellant filed a writ petition alleging illegal and arbitrary acquisition and sought to quash the notification under Section 3D to the extent it affected his land. The learned Single Judge dismissed the petition, holding that the award and notification had concluded acquisition proceedings and that the petitioner was free to pursue other remedies.
Contentions and Judgment:
Senior counsel for the appellant argued that the final approved alignment as per the DPR was from CH 76/400, and deviating to CH 76/100 without proper consideration violated the appellant’s rights. He claimed the objections were not genuinely considered and sought judicial review of the alignment and subsequent notification.
The respondents contended that three alignment options were examined by DPR consultants, and the Ministry of Road Transport and Highways approved the third option, starting from CH 76/100. The objections were considered and rejected with detailed endorsements, and the acquisition notification under Section 3D vested the land in the Central Government free from encumbrances.
The Division Bench upheld the Single Judge's findings, relying heavily on the Supreme Court’s precedent in Union of India v. Kushala Shetty (2011), which limits judicial intervention in matters of project feasibility and alignment unless there is an egregious violation of law or mala fides. The Court observed:
- The objections raised by the appellant were duly considered and rejected by the competent authority with reasoned endorsements.
- The choice of alignment was made by technical experts and approved by the Ministry, reflecting a decision in the larger public interest.
- Judicial review is limited to rare cases where acquisition violates statutory mandates or is tainted with mala fides. No such grounds were established here.
- The land acquisition notification under Section 3D(1) conclusively vests the land in the Central Government, and the Court cannot interfere with the acquisition once validly notified.
The Court dismissed the writ appeal, leaving the appellant free to pursue statutory remedies but declining to set aside the acquisition or notification.
Significance:
This judgment reinforces the principle that courts defer to expert authorities and administrative processes in infrastructure projects, limiting interference to exceptional cases of legal violation or bad faith. It affirms the robustness of the National Highways Act, 1956, as amended, in streamlining acquisition for national projects and underscores the judiciary’s restrained role in technical and policy decisions.
The ruling provides clarity to landowners and authorities regarding the scope and finality of acquisition under the National Highways Act and serves as a precedent for future disputes involving project alignments and land acquisition objections.
Bottom Line:
Judicial review in land acquisition cases under National Highways Act, 1956 is limited. Courts cannot decide on the feasibility or viability of projects unless a violation of law or mala fides is established.
Statutory provision(s): National Highways Act, 1956 Sections 3A, 3C, 3D
Talasani Sravan Reddy v. Union of India, (Telangana)(DB) : Law Finder Doc Id # 3129691